Eskom urgently needs to build 1,400km of new transmission lines annually for the next ten years to expand the grid and connect new energy sources. However, the utility has struggled to meet its targets due to grid constraints in key regions for renewable energy projects.
In the 2023/24 financial year, Eskom aimed to construct 166km of transmission lines but only completed 74km across three projects, delaying the activation of these crucial lines. This setback hampers progress in the government’s energy action plan and the integration of new renewable energy sources.